Aswin 2075
- Clearing and dumping the debris deposits on the foundation of Kasthamandap continued. Dismantling few brickworks previously done in cement mortar was also started. Site investigation was being carried out for information on various stages of developments of Kasthamandap.
- 05 Aswin – Indrajatra festival started.
- Muchulka was carried out to dismantle Gorakhnath mandap and two remaining pavilions in NE and NW corner of Kasthmandap which was severely damaged in 2015 earthquake.
- Draft report on structural analysis of Kasthamandap was submitted by Resilient Structures Pvt. Ltd.
- Basic survey of the levels of existing ilohan was carried out.
- Lab report on the test of sample ma: appa provided by Daxin Barahi Brick Industry was received. Meeting with Daxin Barahi Brick Industry was held to negotiate on unit cost of ma: appa.
- Some discovery: a) old paving layer on north and south side
- Drone Imaging of the foundation of Kasthamandap was carried out.
- The first batch of timber was received from Timber Coorporation Nepal. Written agreement with TCN was carried out for subsequent batches of timber.
- 24 Aswin – Gatasthapana
- Meeting with larger committee for the reconstruction of Kasthamandap was held.
- 30 Aswin – Fulpati. Cleaning campaign on Kasthamandap was carried out with the participation of locals, committee members and staffs.