Schedule/Progress Report

Tree view of Work Schedule/Progress

Kartik 2075

  Dismantling temporary structure of Gorakhnath Mandap was carried out. Total station survey of the foundation walls of Kasthamandap was...

view more

Aswin 2075

Clearing and dumping the debris deposits on the foundation of Kasthamandap continued. Dismantling few brickworks previously done in cement mortar...

view more

Bhadra 2075

Clearing and dumping the debris deposits on the foundation of Kasthamandap continued. The clearing of pavilions on NE and NW...

view more

May10-12

Wood sorting salvaging and Inventory Phase-1 A full report of the whole time period, which has been prepared by Ar....

view more

May-14

Kshama Puja ritual held at site of Kasthamandap. News links The Himalayntimes  

view more

Shrawan-2075

Clearing the debris deposits on the foundation of Kasthamandap started and continued. With agreement from related stakeholders, the debris was...

view more